Watson cited an example of a juice bottling line for which engineers were advised by Toyota experts to eliminate all of the conveyors between machines, because classic Lean principles brand conveyors as excess and unnecessary. The recommendation was in line with the objective of “single-piece flow,” Watson said, with “close-coupling” of machines enabling production pieces to move directly between machines. In this state, when a stoppage occurs on one machine, all the machines on the line must stop, and the condition is used to identify the root cause of the problem.
That’s fine for Toyota, Watson said. But for the juice bottler, what the Toyota experts’ recommendation failed to consider are the differences between automotive production and packaging, not only in the speed of the line, but in the differences in materials being used, he observed. Unlike the steel, glass and rigid polymers that automotive manufacturers work with, packaging materials such as thin plastics and corrugate are highly variable, meaning that frequent machine stops are inevitable, Watson noted. A Lean automotive production line producing 1,500 cars per month might see a line stoppage only once every few weeks. By contrast, a high-speed packaging line running several hundred items per minute, even at Six Sigma quality levels, is likely to see failures several times per hour, Watson said—much too often to stop the entire line for each occurrence.
Buffers needed
As a result, the Lean concepts of “close-coupling” and “single-piece flow” on a high-speed packaging line must be modified to include the appropriate amount of accumulation or buffer to accommodate the inevitable “micro-stops” that will occur, Watson explained. To be sure, having too much accumulation on a line amounts to waste. But adding just enough buffer in the right places allows operators to deal with a jam while the line continues to run, Watson noted.
Various tools exist for calculating where and how much accumulation to add, including use of overall equipment effectiveness (OEE) techniques, and more recently, computer simulation, Watson said. “You’ll have to pay a little money to do either one of these, but compared to buying a machine, specing it, installing it and running it before you can do the calculation, the cost is minimal.”
In general, those looking to deploy Lean in their plants must remember the differences between their own operations and those of Toyota, Watson advised. “When Toyota developed these concepts, they called it the Toyota Production System because they did it for Toyota. And Toyota makes cars,” he told the Pack Expo audience. “So unless you work for Toyota and you make cars, there’s probably not going to be a perfect fit between what they do and what you do.”
Given that successful Lean Manufacturing initiatives produce more efficient operations, it’s not surprising ...