Feature Article
|

DuPont’s Alarm Management Plan

Print Reprint
     
When DuPont began its efforts to overhaul its alarm management system, the plan called for very specific steps in the process.

 

1. Leadership. This is a big deal, says Nick Sands, manufacturing technology fellow at DuPont. “For the first 20 years, we were improving from the bottom up,” he recalls. “In the last 20 months, corporate was all over it, and we got it done.”

2. Monitoring. Get your measurements in place first, Sands recommends. “Get your data set for about a month. Wait to fix things.”

3. Benchmark. Interview the operators to find out what they think about how the alarm system performs.

4. Quick hits. “Get rid of those things going off,” Sands says. DuPont sometimes had alarms going off 150,000 times a week. In one case, an alarm was going off repeatedly throughout the day. It turned out to be caused by a fan every time a light was turned on in the restroom. “Nobody knew how bad it was,” Sands says. Getting nuisance alarms under control makes considerable improvement. “People start to believe that things can change; that it doesn’t always have to be that way.”

ADVERTISEMENT

5. Training. DuPont trained 523 people through a two-day class. This had to be done before moving on to step 6, Sands says.

6. Philosophy. “It’s going to guide you year after year, operator after operator,” Sands says. “If you want to make sure you have an alarm management program that’s sustainable over time, you have to have a philosophy in place.”

7. Rationalize. See more in the main story about rationalization.

8. Improvement. It’s a never-ending process, requiring continuous improvement.

9. Audit. What are the gaps? What needs to be improved on?

>> Read Automation World's complete coverage on alarm management: It's Hard to Keep a Bad Alarm Down.

COMPANIES IN THIS ARTICLE: DuPont
1

Comments

ISA 18.2 does define the term "Instrument diagnostic alarm" as "An alarm generated by a field device to indicate a fault (e.g., sensor failure)." but does not speak much about the specifics. This will be the scope of the ISA108 standard which is under development. In the mean time, learn more from the white papers and guides found here: http://www.eddl.org/DeviceManagement/Pages/DeviceDiagnostics.aspx#Institutionalizing The NAMUR NE107 recommendation is key here: http://www2.emersonprocess.com/siteadmincenter/PM%20DeltaV%20Documents/Whitepapers/WP_Configuring_FF912_Alarms.pdf

Add new comment

Newsletters

Don't miss intelligence crucial to your job and business!
Click on any newsletter to view a sample. Enter your email address below to sign up!
Each newsletter ranges in frequency from once per month to a few times per month at most.
The best of the essentials!
Secrets to Automation Project Success

Sign up to receive timely updates from our editors and download this FREE Automation Project Survival Guide. It’s packed with field-tested best practices from industry experts that can help make your next automation project a success.

x