Large automation upgrade projects for manufacturing facilities are driven by a multitude of factors, including increased regulations, changing consumer behaviors and the lure of greater operational efficiencies for legacy plants. But the path forward is not always simple.
When a Canadian manufacturer of intravenous (IV) and peritoneal dialysis solutions recently launched a multimillion-dollar upgrade for its 180,000-sq-ft processing and packaging facility, it called on Grantek Systems Integration to bridge the most complex engineering challenges of its automation initiative.
The project overhauled the manufacturerâs preexisting filler supply tanks and clean-in-place (CIP) system and updated all of the process piping to support better drainage, add product recirculation functionality and allow for automated connection of multiple tanks to multiple filling lines.
The facility consists of three filling lines serving two automated fillers and three manual fillers, and these lines are fed by the 13 solution tanks.
The initiative also added a comprehensive fleet of instruments on the processing side to help regulate and monitor solution flow. These included automatic solenoid valves, GEA Tuchenhagen mix-proof valves, analog control valves, back-pressure valves, Endress+Hauser mass and magnetic flow meters, and variable-frequency drives.
The challenge begins
The massive capital project encountered integration challenges after a third-party system integratorâfollowed by the pharmaceutical companyâs internal automation staffâwere unable to resolve control logic issues associated with the routing and fillers. The in-house staff tried on-the-fly patches, which only contributed more troubles as the company moved toward the validation stage.
At this point, the manufacturer enlisted Grantek to finish the automation engineering role for the most complex lineâwhich included three fillers and multiple tank batchingâin under three months.
Grantek faced the challenge of having to update the process design, clarify the controls narrative and strategy, and then write the code within a short time span. The ControlLogix programmable logic controller (PLC) program already incorporated logic from the existing production line, but needed to integrate the logic from the other lines. Each of the three fillers of this complex line consisted of a PLC, human-machine interface (HMI) and the newly added CIP functionality. The fillers were a mix of Rockwell Automationâs ControlLogix controllers, PLC-5 controllers and PanelView HMIs. The control was Ethernet-based and communicated to the CIP PLC, and included the Schneider Electric Vijeo Citect HMI platform developed in-house.
âThe client wanted something manageable, using standard building blocks,â says Parm Pawan, senior manager at Grantek. âPlantPAx add-on-instructions (AOIs) were a perfect addition, but [the client] also wanted our phase engine AOI that has been developed over time and used in many applications.â
While PlantPAx AOIs provide the facility with robust diagnostics for the instruments, Grantekâs phase engine AOI templates create a marshaling system to request devices and confirm route destinations. The design at the pharmaceutical facility provides operators the ability to choose different phases for moving liquid to fillers or to execute CIP actions. Through the phase engine AOI logic, the operator can request various tank and filler route combinations.
Proximity switches disclose when shared piping is in place for operation, Pawan explains, adding, âThe system wonât start filling if they donât have the shared piping match the phase.â
Confronted by compressed commissioning and validation schedules, Grantek relied on code auto-generation to replicate instrument configuration and behavior. After perfecting the routine that controls one valve, the system integrator wrote and used auto-generation scripts to produce control logic for more than 50 other valves. Grantek also employed a template process to auto-generate similar phases.
Grantek rigorously modeled and verified the phase engine approach, as well as different operation scenarios offsite, before commissioning started. âWith any process project, there has to be room for engineering variables and set points at the site,â Pawan says. âWhen product is in the pipes, thereâs some variability and configuration needed onsite.â
Also included in this capital project was the addition of a flexible and robust HMI platform, which now offers the ability to view multiple stations throughout the facility. The pharmaceutical companyâs sister plant in Australia also launched an update recently, and the HMI platform was the only component standardized between the two sites.
âOperators have mobile devices to monitor tank states, fillers and multiple production lines,â Pawan says. âThe data monitoring includes product flow and types, route destinations and availability.â Remote monitoring from outside of the plant is now part of the platform.
With such a significant investment in an older facility, the company needed an experienced integrator to solve the automation engineering challenges for its complex production line and successfully navigate validation. Grantek further assisted the client with 24-hour onsite support during the initiativeâs dry and wet validation testing.
About the Author
Grant Gerke
Digital Managing Editor

Leaders relevant to this article:
