First line of Northland’s Kaunisvaara iron ore mine goes online

Feb. 28, 2013
Power and automation company ABB announced that it recently completed commissioning of the integrated electrification and automation system for the first process line of Northland Resources’ Kaunisvaara iron ore concentrator plant.

Power and automation company ABB announced that it recently completed commissioning of the integrated electrification and automation system for the first process line of Northland Resources’ Kaunisvaara iron ore concentrator plant.

The site is located approximately 100 km north of the Arctic Circle, in Sweden. The initial orders were awarded in the first quarter of 2012 by Metso Minerals and Northland Resources.

The extremely tight schedule made this project unique: ABB delivered its first equipment only two months after contract awarding – production started merely seven months later on December 4, 2012.

“This is truly a remarkable achievement by the Northland team together with our key suppliers. They have been able to keep up with the demanding time schedule that we set up”, said Karl-Axel Waplan, President & CEO of Northland. “This has only been possible thanks to the tremendous dedication of the project management team and the competent staff. The close partnership with our contract partners has played a vital role in our success.”

ABB’s electrification and automation solutions will allow Northland Resources to achieve optimal operational conditions to reach highest production at lowest energy costs. The scope of supply included nine containerized electrical rooms with embedded medium- and low-voltage switchgear, variable-speed drives and motor control centers, integrated with a plant-wide process automation system using ABB’s Extended Automation System 800xA.  ABB’s delivery also included fiber optic network equipment cabling, cable trenching, installation material, engineering, commissioning, installation supervision and project management services.

A previous order included one sophisticated dual pinion low-speed mill drive system (2x 5800 kW). This drive system consists of converter transformers, the frequency converter ACS6000 and synchronous motors and is currently in its final commissioning stage.

Northland plans to produce 1.4 million dry metric tons (dmt) of high-grade iron ore concentrate in 2013 and 3 million dmt in 2014. The company expects to reach the production capacity of 4 million dmt per year in the beginning of the third quarter of 2014.

>>For more information on this product, click here

Companies in this Article

Sponsored Recommendations

Food Production: How SEW-EURODRIVE Drives Excellence

Optimize food production with SEW-EURODRIVE’s hygienic, energy-efficient automation and drive solutions for precision, reliability, and sustainability.

Rock Quarry Implements Ignition to Improve Visibility, Safety & Decision-Making

George Reed, with the help of Factory Technologies, was looking to further automate the processes at its quarries and make Ignition an organization-wide standard.

Water Infrastructure Company Replaces Point-To-Point VPN With MQTT

Goodnight Midstream chose Ignition because it could fulfill several requirements: data mining and business intelligence work on the system backend; powerful Linux-based edge deployments...

The Purdue Model And Ignition

In the automation world, the Purdue Model (also known as the Purdue reference model, Purdue network model, ISA 95, or the Automation Pyramid) is a well-known architectural framework...